Zoomlion 33X-42 Truck-Mounted Concrete Boom Pump
Challenge Concrete Pumping needed independent proof that its 33 m boom pump was safe, compliant and ready for another year on site. Cossack Inspections carried out a full annual inspection to AS 1418 and AS 2550 and issued certification.

Plant Details
Keeping a Working Pump Compliant
Concrete pumps work hard: high-pressure hydraulics, a multi-section boom, outriggers on uneven ground and delivery pipes under constant wear. Under WHS Regulation 2022 the owner needs documented, periodic inspection by a competent person.
The pump also needed its log book, manuals, VSB6 modification plate and previous inspection records confirmed before the new certificate could be issued.
Scope of Work
- Documents: operator manual, log book, previous boom inspection
- Boom sections, lugs, pins, sheaves and hazard decals
- Slew system, slew bolts, bearing and pinion
- Outriggers and stabilizer controls
- Hydraulic rams, luff cylinders, hoses and oil cooler
- Air, electrical, chassis and drive systems
- Delivery pipes, clamps, safety clips and emergency stops
Eight Systems, One Checklist
Boom & Attachments
Base and extension sections, boom lift cylinders, lock valves, sheaves, rope systems, angle indicator.
PASSEDRevolving Frame
Frame, mounting lugs and pins, counterweight, control levers, remote controls, emergency stop, VSB6 plate.
PASSEDSlew System
Slew cylinder, brake, gear, pinion, bearing, bolts, backlash and smooth operation.
PASSEDHydraulic System
Reservoir, pumps, relief and flow control valves, filters, hoses, oil cooler, steering cylinder.
PASSEDAir Systems
Compressor, reservoirs, brake chambers and valves, drain valves, air lines and gauges.
PASSEDElectrical System
Battery box, cables and isolator, all lights, beacon, horn, back-up alarm, switches and relays.
PASSEDChassis
Frame, suspension, axles, brakes, parking and emergency release, wheels and tyres, fire extinguisher.
PASSEDDrive Systems
Engine mounts, cooling, fuel system, belts, transmission, PTO pump drives, muffler and spark arrestor.
PASSEDInspection Gallery
Photos captured on site during the inspection. Click any image to enlarge.












Certificate of Annual Inspection
On completion the competent person signed a Certificate of Annual Inspection. A green inspection sticker showing the inspection date and next due date was fixed to the plant.
The inspection was performed in accordance with AS 1418.1, AS 1418.15, AS 2550.1, AS 2550.15, WHS Regulation 2022 and the manufacturer's specification.

- Certificate No.
- COSS CC A 262-3/26 CP
- Inspection Date
- 4 March 2026
- Next Due
- 4 March 2027
- Location
- Port Kennedy, WA
- Plant
- Truck Mounted Concrete Boom Pump
- Competent Person
- Dibyendu Das, MEng (Mech), MIEAust
- Supervisor
- Ken Hodges
- Inspection Body
- Cossack Inspections (NATA / Engineers Australia)
Certified and Back on Site
Fit for Use
Machine considered suitable for use at the time of inspection.
Records Verified
Log book, manuals, VSB6 plate and prior inspection details confirmed.
Visible Compliance
Green sticker on the plant shows the date and next due date.
12-Month Cover
Next annual inspection due March 2027.
Need Your Concrete Pump Inspected?
Talk to our competent persons about annual and major inspections for pumps, cranes and access equipment.
Call 0408 820 351 Email Us